Phase 1 & 2 West side Action
2022 — Phase 1
1. Completed: The 11 tracks of DUT station and the 5 tracks of the joint line return loop were laid before moving to my current location. So far in 2021 I have laid the 2 additional tracks on the joint line return loop and most of the remaining trackage for modules 1 & 1a.
2. Completed: A circle of track on modules 5 and 6a which will provide for loco testing and as a return loop to both the South and West lines.
3. July/August/September: Laying all of the track specified in the new Phase 1. Followed by ballasting, painting and scenery for modules 7 & 8. Install electrics for main line signals. Dirt ground cover where future yard tracks are to go.
4. Oct/Nov/Dec: Build the kits for East Denver Belt Line, Burnham loco facility, the Arapahoe Power Plant, the PSC gas Plant and the Denver Market & Produce Terminal (Wazee Market).
2023 — Phase 2
Q1. January/February/March : Lay the DRGW main line from the East portal of the Moffat Tunnel to Glenwood Springs. Followed by ballasting, painting, scenery and kit building for modules 11 & 12.
Q2. April/May/June: Lay the track for the 7 staging tracks of the Grand Jct loop. Set up route control using an NCE Mini panel.
Q3. July/August/September: Lay the track for Golden and Glenwood Springs industries .Build the kits.
Q4. Oct/Nov/Dec: Finish building phases 1 & 2 to completion.